A thermal plant in CIRP is valued twice. First as a working station, with its PPA, fuel linkage and approvals. Then as equipment sold off in a hurry. The Committee of Creditors bargains over the gap between the two. So both must rest on the same site evidence.
How it usually unfolds
The Resolution Professional has seven days and a 600 MW station. It has not run at full load in two years. The coal linkage has lapsed. One unit is under repair, and the PPA is in dispute. The lenders want to know one thing: is this plant worth saving?
Our engineers start on site, not in the data room. They inspect and grade the boilers, turbines, coal-handling plant and ash pond. A turbine that was preserved well is worth far more than one that was just switched off.
Then the two values take shape. Fair value assumes a buyer who can restore fuel supply and sell power. Liquidation value assumes the plant is sold piece by piece within months. The CoC sees both, with the reasons behind each. It can then judge every resolution plan against them.
Illustrative scenario drawn from the kinds of mandates RNC handles. It does not describe a specific client.
What changes the value
| Decision point | Why it matters |
|---|---|
| PPA status | A PPA that holds up supports a fair value based on income. A disputed one pushes the valuer towards cost and weighted scenarios. |
| Fuel security | With no linkage and no workable import route, a restart is a guess. Fair value then moves closer to replacement cost. |
| Preservation of equipment | Units that were kept well hold their value. Neglected ones need large cuts for wear and age. |
What to have ready
- Asset register for each unit and the last overhaul reports
- PPA, fuel supply and transmission agreements, with the status of any dispute
- Environmental consents and how long they are valid
- Site access for engineers to every unit