Power project valuation finds what a power plant is worth for a set purpose. That may be an IBC case, a lender’s recovery choice, a sale, insurance or the accounts. A running plant with a PPA is usually valued on discounted cash flows. A plant that is half-built or stranded needs two cases: the cost to finish it, and what a piece-by-piece sale would bring. Both rest on an engineer’s site visit.
When does a power asset need a valuation?
| Trigger | What is needed | Rule or source |
|---|---|---|
| Plant admitted into CIRP or liquidation | Fair value and liquidation value from two registered valuers for each asset class | Reg. 27 and 35, CIRP Regulations |
| Lender restructuring or one-time settlement | Asset and enterprise value, as a going concern and in a recovery case | Lender policy, RBI prudential framework |
| Acquisition or sale of a plant or portfolio | Enterprise value, a DCF based on the PPA, and technical due diligence | Companies Act, SEBI where listed |
| New project or added capacity that needs a loan | Techno economic viability (TEV) study | Bank empanelment rules |
| Project being built with a lender’s money | A lender’s independent engineer checks cost and progress | Facility agreement |
| Plant insurance renewal | Reinstatement value to set the sum insured; ALOP checks while the plant is built | Policy terms, IRDAI |
| Year-end accounts with signs of impairment | Recoverable amount under Ind AS 36 | Ind AS 36 |
Which valuation method fits which power asset?
| Asset situation | Approach we use |
|---|---|
| Running thermal plant with a PPA | DCF on the agreed tariff, fuel cost and PLF; the cost approach as a cross-check |
| Thermal unit still being built | One case to finish it (new capex and timeline) and one to sell it piece by piece; going concern for any unit that runs |
| Captive plant inside a factory site | Three cases: it keeps supplying power, it is sold with the host plant, or its assets are moved |
| Hydro project with physical damage | Asset-based going-concern value of the civil works and the kit that can be saved, with a risk discount for the restart |
| Solar and wind parks | DCF on the PPA tariff, expected output and wear over time; land and right-of-way are valued on their own |
| Makers of equipment and towers | Income and asset approaches, adjusted for metal prices and the order book |
Can anyone really value a half-built plant?
Yes. Lenders brought us a coal plant in South India. One unit was running. The second was unfinished. The EPC contracts had ended, and imported equipment sat idle. Neither unit had a PPA or a fuel deal. Earlier opinions gave a single number, and no bidder trusted them.
We built two cases instead. In the first, both units are finished and run, and we allow for the cost and time to finish. In the second, the running unit is a going concern, and the unfinished unit is valued for salvage and resale. The lenders could see the cost to finish next to the sale value. They chose to sell, and ran the sale knowing their floor. Read the case study.
Why not simply run a DCF?
A DCF is only as good as its cash flows. A flood washed away much of the equipment at a mid-scale hydro project. It had no PPA, and its clearances had lapsed. Any revenue forecast was guesswork. So we valued the civil works, the machines that could be saved and the cost to finish. Then we took a clear discount for restarting the plant and for new approvals. The resolution professional used the range to set a reserve price. It drew bidders who knew what they were buying. Read the case study.
What if the plant cannot run on its own?
A captive plant of nearly 500 MW relied on its host steel plant. The host gave it water, raw materials, a way to send out power and waste disposal. Both were in separate CIRPs. We valued three futures: supply goes on, a sale with the current set-up, and moving the assets. The lenders chose to sell, with a figure for each outcome. Read the case study.
Will the value stand up in front of the CoC and bidders?
It will, if it is built the way the rules expect. Our reports follow International Valuation Standards and the IBBI report format. They show every case, discount and source. Site visits back up our engineering calls, such as wear on idle imported equipment.
Pitfalls we see most often
- Assuming contracts that no longer exist. Ended EPC contracts, lapsed PPAs and missing fuel links change the basis of value.
- Ignoring the risk of new approvals. A buyer usually needs fresh approvals and clearances.
- Treating idle machines as new. Only a site visit shows the wear.
- Missing shared facilities. Captive plants often cannot run without their host.
- Too little cover while building. Sum insured and ALOP cover should grow with the project.