Substations and transmission assets should be insured at what it would cost to rebuild them today. That includes transformers with long lead times, foundations, erection and commissioning. Book value is almost always too low. The average clause then turns that gap into a smaller claim.
How it usually unfolds
A utility renews its property policy every year at book value. Transformers bought a decade ago sit in the books at a fraction of what they cost now. The risk manager has started to worry.
We build the reinstatement value asset by asset. We use today’s prices for transformers, switchgear and conductors. We add civil works and foundations, erection and testing. For imported equipment we add freight and duties. We flag long lead times, because they also matter for business-interruption cover.
The new sum insured is much higher than book value. The premium rises a little. But the risk of a claim cut in proportion after a fire or storm largely goes away.
Illustrative scenario drawn from the kinds of mandates RNC handles. It does not describe a specific client.
What changes the value
| Decision point | Why it matters |
|---|---|
| Imported equipment | Moves in currency and duties can shift the rebuild cost sharply. |
| Lead times | Transformers that take long to arrive affect business-interruption periods as well as property cover. |
| Civil and erection costs | These are often forgotten, yet they are a large part of the cost to rebuild. |
What to have ready
- Asset register with specifications and the year each asset was installed
- Recent purchase orders for similar equipment
- Current policy schedule and sums insured
- Single-line diagrams for key substations